What this project set out to answer
What are the key issues at the Manlius Town Hall and Police Station, how should they be prioritized, what options exist for addressing them, and how can they be communicated transparently to the community?
Town staff have long known of facility issues across both buildings. In response, the Town Board initiated a community engagement process and convened a study group of community representatives. Our Maxwell team was brought on to compile and refine that information into a clear, data-driven set of findings and options the community can weigh.
How we identified and addressed the issues
We grounded the work in the community's own priorities, then built outward through site visits, peer comparison, legal research, and cost analysis.
- Gathered community information and reviewed engagement feedback and supplemental documents
- Toured the Manlius Town Hall and Police Department, plus the DeWitt and Camillus town halls for comparison
- Held a community listening session on June 8th with a focus group of study-group applicants
- Researched the legal requirements governing the facilities
- Categorized and prioritized the concerns we found
- Developed a set of options and ran a cost-benefit analysis on each
What the community told us
The listening session shaped everything downstream. Residents asked for a clear list of problems, insisted that transparency was essential, and named safety and ADA accessibility as top priorities. They wanted decisions to be data-driven, were wary of tax increases, and asked that the facilities be made functional rather than impressive. Many also wanted to see how Manlius compares to neighboring towns.
Where Manlius stands
Compared with its neighbors, Manlius is the largest town by both population and area, and has the highest median household income — yet it carries the second-highest tax base, the third-highest budget, and the lowest property tax revenue. In short: larger and wealthier, but facing greater problems with fewer resources.
Peer towns set a useful bar. DeWitt operates with a larger staff and stronger security — bulletproof glass and doors, interconnected private workspace, and full ADA compliance. Camillus has a designated buildings supervisor, an electronic lock and badging system, and is actively investing in ADA compliance such as an elevator retrofit.
The 32 issues, organized
We sorted every issue across both buildings into four categories — Accessibility, Security/Safety, Operational, and Electrical — and three priority tiers: Legally Required, Should Fix, and Ideally Fix. That structure lets the Town see at a glance what it must do, what it should do, and what it could do.
Five paths forward
Each option packages the issues differently, trading up-front cost against how completely the facilities' problems get solved. The cost-benefit analysis details the financials behind each.
How the options compare
The headline figures from the cost-benefit analysis. All dollar amounts are present value over a 30-year horizon, discounted at 4%; the full model behind these numbers is in the Deliverables section below.
| Metric | ADo Minimum | BFull Rebuild | CSplit | DPurchase | EPurchase + Min |
|---|---|---|---|---|---|
| Upfront project cost | $1.2M | $47.3M | $44.5M | $20.8M | $8.1M |
| 30-year net cost (PV) | $23.7M | $51.0M | $49.8M | $22.7M | $20.6M |
| Est. tax increase, median home | $0 | $199/yr | $187/yr | $86/yr | $32/yr |
| Solves the building problem | No — defers | Yes — fully | Yes — partial | Yes — partial | Yes — partial |
| Estimate confidence | Lower | Highest | Good | Lowest | Lowest |
Note: Option E has the lowest upfront cost but carries a deferred Town Hall rebuild in Year 30, which makes Option D the lower cost once measured across the full 30 years.
Which option fixes what
This is the slate residents asked for: every issue we identified, mapped against the five options. It shows, issue by issue, which paths forward would resolve it — so the trade-offs are visible rather than buried in a cost figure.
| Priority | Issue | A | B | C | D | E |
|---|
Priority tiers: Legally required, Should fix, and Ideally fix. The full slate, including issue categories, is in the downloadable file in the Deliverables section.
The full body of work
Everything the team produced is collected here — viewable in the browser and downloadable as the original files.
CBA Guide
ReadyThe companion guide to the cost-benefit analysis — the purpose of the study, a walkthrough of each scenario, why specific cost items are included, and where every number comes from.
Cost-Benefit Analysis
ReadyThe full CBA model comparing all five options across capital cost, 30-year present value, tax-levy impact, and monetized benefits — with per-scenario detail, assumptions, and sourced parameters. The headline figures are summarized in the table above.
ADA Justifications
ReadyThe detailed accessibility analysis behind the findings — each Town Hall and Police Station issue tied to the specific ADA requirement it addresses, organized as must, should, and could address, with the cost thresholds used to judge undue burden.
Non-ADA Issue Explanations
ReadyPlain-language explanations of every non-accessibility issue in the slate — security, operational, electrical, and space concerns across both buildings — describing what each problem is and why it matters, grouped by priority tier.
Slate of Options to Address Issues
ReadyThe full issue-by-option matrix — every Town Hall and Police Station issue, by category and priority tier, mapped against which of the five options resolves it. The interactive version is in the Slate section above.
Communications & Outreach Strategies
ReadyStrategies for sharing the findings and including residents in the re-envisioning process — a dedicated Town web page that links this site, mailed handouts, short videos documenting accessibility issues, and updates through Town newsletters and forums.
Final Presentation
ReadyThe full slide deck delivered to the Town — project background, community engagement, peer comparisons, the 32 issues, all five options with space-and-tradeoff detail, and the cost analysis.
Sources and supporting materials
Every source consulted across the project — the commissioned professional studies, the Town's own records, peer-town data, and the government and professional standards behind the findings. Figures rest on authoritative sources rather than commercial or marketing material.
Commissioned studies & estimates
- VIP Architectural Associates, D.P.C., with IPD Engineering and Keplinger Freeman Associates. Manlius Town Hall Building Conditions Assessment (November 2024).
- Trophy Point Construction Services Consulting. New Town Hall, Court and Police Dept., Town of Manlius — Feasibility Study (2025).
- King + King Architects; Miller Engineering; TL Brown Management Group. Town of Manlius Municipal Building Study — Final Report (2018).
Town & peer-town records
- Town of Manlius. 2025 Town Budget and 2026 Final Budget; National Grid utility history; buildings-contractual expense records. townofmanlius.org
- Town of Manlius Assessor. Assessment records — total taxable value ($4.8B) and median home assessed value ($332,100).
- Town of Manlius / Village of Manlius. Police lease agreement (2025).
- Town of Camillus. 2025 Budget Preparation Publication: Revenue Report (November 2024).
- Town of Cicero. 2026 Final Budget, Town of Cicero in Onondaga County (November 2025).
- County of Onondaga, Department of Finance, Office of Real Property Tax Services. 2025 County of Onondaga Rate Book: Town/County Assessed Valuations, Taxes and Tax Rates (January 2025).
- Town of DeWitt. Town budget documents. dewittny.gov
- U.S. Census Bureau. 2023 American Community Survey 5-Year Estimates — Towns of Camillus, Cicero, DeWitt, and Manlius, NY. data.census.gov
Government & professional standards
- U.S. Department of Justice, Civil Rights Division. Americans with Disabilities Act of 1990, As Amended; 2010 ADA Standards for Accessible Design (Title II). ada.gov
- U.S. Access Board. Chapter 4: Accessible Routes. access-board.gov
- ADA Checklist for Existing Facilities (2016). Institute for Human Centered Design; ADA National Network. adachecklist.org
- International Association of Chiefs of Police. Police Facilities Planning Guidelines. theiacp.org
- New York State Department of Labor. Public Employee Safety and Health (PESH) Bureau. dol.ny.gov
- New York State Office of the State Comptroller. Real Property Tax Cap. osc.ny.gov
- New York State Archives. Local Government Records Law, Article 57-A, Arts & Cultural Affairs Law. archives.nysed.gov
- Agency for Toxic Substances and Disease Registry. Asbestos — Public Health Statement (2016). cdc.gov
- European Commission. Guide to Cost-Benefit Analysis of Investment Projects. Publications Office of the European Union.
- U.S. Office of Management and Budget. Guidelines and Discount Rates for Benefit-Cost Analysis of Federal Programs (Circular A-94).
- Hinge Health. Knee Pain When Squatting? Causes & Exercises That Can Help (2026). hingehealth.com